Please read through this page carefully to ensure that you follow the process and submit the right forms at the right times. Failure to do so may result in you incurring CIL liability and/or surcharges that could have been avoided.
You should submit Form 1: Additional Information Form for every full, reserved matters and domestic planning application for the types of development included in the CIL Charging Schedule
Form 1: Additional Information Form
The CIL Planning Application Additional Information Requirement Guidance will help you to complete this form.
Additional Information Guidance Note
Note: A planning application will be invalid without a correctly completed Additional Information Requirement Form.
You should submit Form 2: Assumption of Liability together with Form 1 with the planning application submission.
Form 2: Assumption of Liability
If the liable party changes you can withdraw or transfer the liability at any time before the development commences using Form 3 or 4 (whichever is applicable).
Form 3: Withdrawal of Assumption of Liability
Form 4: Transfer of Assumed Liability
Some developments are exempt or are offered relief from paying CIL. If you consider that your development is exempt or should be offered relief from paying CIL you must submit the applicable exemption or relief claim form before you commence development.
Form 7: Self Build Exemption Claim Form Part 1
Form 7: Self Build Exemption Claim Form Part 2
Form 8: Residential Annex Exemption Claim Form
Form 9: Residential Extension Exemption Claim Form
Form 10: Charitable and/or Social Housing Relief Claim Form
Form 12: Further Charitable and/or Social Housing Relief Claim
Form 13: Further Exemption Claim
Shortly after granting planning permission we will issue a Liability Notice (to the person(s) named in Form 2: Assumption of Liability). This will detail how much CIL will be payable (even if this is £0) which will become due on the date of commencement as detailed in Stage 4.
Before you commence work on site (including demolition) you should submit Form 6: Commencement Notice to us, letting us know the exact date that commencement will take place. This Form must be submitted at least one clear working day in advance of commencement.
Note: The correct CIL form must be submitted, which is different from any similar form required by Building Control or Planning Enforcement.
It is important that you wait until you receive an acknowledgement from us that this form has been received. Failure to do this before commencement will result in the loss of any right to pay by instalments and result in a surcharge.
If you have received an exemption or relief from the levy, failure to submit this form, and for it to be received by the collecting authority, before commencing your development will result in a surcharge being applied equal to 20% of the chargeable amount or £2,500, whichever is the lower amount.
We will issue a Demand Notice from the date of Commencement. The Demand Notice will state the amount of CIL to be paid, and when and how it should be paid.
We have an instalment policy in place which allows larger CIL payments to be spread over several instalments - Instalment Policy
Note: If the date given on the Commencement Notice is delayed, the applicant/agent can issue a further Commencement Notice using Form 6.
If you are undertaking a development in phases, and you have overpaid against an earlier phase, you may make a Phased Credit Application to roll the overpayment forward to later phases.