Latest Updates
Works Completed — full public access
- Thorney Bay
- Labworth Cafe
- Leigh Beck
Works ongoing
- Concord Beach — Wastern and Eastern tidal pool including Concord Beach closed from September 2024 until Spring 2025
- Riverside revetment works September 2024-May 2025
- Landside reinstatement — July 2025
- Eastern Esplenade -Works ongoing until September 2025
- Riverside revetment works March 2024-June 2025
- Landside reinstatement — September 2025
- Chapman Sands — Marine Parade and Haul Road
- Riverside revetment works November 2023-Winter 2024
- Landside reinstatement — January 2025
Concord Beach
The ongoing revetment replacement works at Concord Beach are a crucial step in maintaining the integrity of the tidal defence.
Both tidal pools, including Concorde Beach, are closed until Spring 2025. We will not be replacing or improving the external structure of the existing tidal pools.
What are we doing with the sand from Concord Beach?
The sand will be temporarily removed and stored off-site in a secure location on the island. This measure is crucial to prevent any contamination or loss of sand during the construction phase. Once the revetment is restored and the area deemed safe, the sane will be replaced to its original position.
3D model showing what Concord Beach will; look like once pedestrian access enhancements and revetments works are completed.